business-northeast-logo

Monthly Oil Production report for August 2021

BNE ADMIN


Spread the love

  1. Production of Crude Oil

Crude oil production during August 2021 was 2518.56TMT, which is 5.98% lower than the target for the month and 2.29% lower when compared with production of August 2020. Cumulative crude oil production during April-August, 2021 was 12480.21TMT, which is 3.33% and 3.15% lower than the target for the period and production during the corresponding period of last year respectively. Unit-wise and State-wise crude oil production are given in Annexure-I. Unit-wise crude oil production for the month of August 2021 and cumulatively for April-August, 2021 vis-à-vis the same period of last year has been shown in Table-1 and month-wise in Figure-1.

Table-1: Crude Oil Production (in TMT)

Oil CompanyTargetAugust (Month)April-August (Cumulative)
2021-22 (Apr-Mar)*2021-222020-21% over last year2021-222020-21% over last year
Target*Prod.*Prod.Target*Prod.*Prod.
ONGC20272.881753.491642.761708.2396.178439.438119.848515.1995.36
OIL3182.60262.25253.51242.98104.341273.451249.151239.98100.74
PSC Fields7718.52663.07622.29626.3299.363197.313111.223131.2699.36
Total31173.992678.812518.562577.5297.7112910.2012480.2112886.4396.85

Note: Totals may not tally due to rounding off.*: Provisional

Figure-1: Monthly Crude Oil Production 

Unit-wise production details with reasons for the shortfall are as under:

  1. Crude oil production by ONGC in the nomination blocks is less than monthly target of Aug’21 (6.31%) as well as April – Aug’21 target (3.79%). Also, it is less than actual production in corresponding month and period of last year i.e. Aug’20 (3.83%) & Apr-Aug’20 (4.64%). Reasons for shortfall in production are as under:
  • Less than anticipated production from WO-16 cluster due to delay in mobilization of MOPU Sagar Samrat.
  • Less than anticipated production from Cluster-8 fields due to delay in inputs as installation of wellhead platforms delayed due to COVID-19 impact.
  • Consequential loss in oil production due to conditions created by cyclone Tauktae.
  1. Crude oil production by OIL in the nomination blocks is higher than actual production in corresponding month and period of last year i.e. Aug’20 (4.34%) & Apr-Aug’20 (0.74%).  However, it is less than monthly target of Aug’21 (3.33%) as well as April – Aug’21 target (1.91%). Reasons for shortfall in production as compared to target is as under:
  • Less than planned contribution from workover wells, drilling wells and old wells.
  1. Crude oil production by Pvt/JVscompanies in the PSC/RSC regimeis less than monthly target of Aug’21 (6.15%) as well as April – Aug’21 target (2.69%). Also, it is less than actual production in corresponding month and period of last year i.e. Aug’20 (0.64%) & Apr-Aug’20 (0.64%). Reasons for shortfall in production as compared to target is as under:
  • RAVVA (Cairn Energy India Ltd): Production shortfall is due to injectivity issues in few wells that caused the lower productivity.
  • RJ-ON-90/1 (Cairn Energy India Ltd): Production is lower due to downtime on account of well failures and Diesel Generator breakdown across fields. Also, delay in polymer start up led to lower productivity.
  • CB-ONN-2000/1 (GSPC): Not enough production from few wells due to reservoir issues and possible casing and sub surface assembly damage. Also, minor shortfall wells on account of power failure has affected the production.
  • CB-ONN-2004/2 (ONGC): Two development wellscould not be drilled as planned in Q1 FY2021-22. Also, a newly developed well is under performing, thus, affecting the production rate.
  • MB/OSDSF/B80/2016 (Hindustan Oil Exploration Company Ltd.): Delay in commencement of production.
  1. Production of Natural Gas

Natural gas production during August 2021 was 2923.94MMSCM, which is 20.23% higher when compared with production of August 2020 but 10.14% lower than the monthly target. Cumulative natural gas production during April-August, 2021 was 13985.76MMSCM, which is 19.94% higher than production during the corresponding period of last year but 6.39% lower when compared with a target for the period. Unit-wise and state-wise natural gas production is given in Annexure-II. Unit-wise natural gas production for the month of August 2021 and cumulatively for the April-August, 2021 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.

Table-2: Natural Gas Production (inMMSCM)

Oil CompanyTargetAugust (Month)April- August (Cumulative)
2021-22 (Apr-Mar)*2021-222020-21% over last year2021-222020-21% over last year
Target*Prod.*Prod.Target*Prod.*Prod.
ONGC23335.102002.071743.541920.5590.789595.248526.139196.7192.71
OIL2949.65251.06256.59188.59136.051235.251180.191041.14113.36
PSC Fields11834.601000.66923.82322.77286.224110.524279.451422.52300.84
Total38119.353253.792923.942431.91120.2314941.0113985.7611660.37119.94

Note:  Totals may not tally due to rounding off. *: Provisional

Figure-2: Monthly Natural Gas Production

  1. Natural gas production by ONGC in the nominationblocks is less than monthly target of Aug’21 (12.91%) as well as April – Aug’21 target (11.14%). Also, it is less than actual production in corresponding month and period of last year i.e. Aug’20 (9.22%) & Apr-Aug’20 (7.29%). Reasons for shortfall in production as compared to target are as under:
  • Less than anticipated production from WO-16 Cluster due to delay in mobilization of MOPU Sagar Samrat.
  • Less than planned production from few wells due to certain reservoir related issues.
  • Delay in commencement of gas production from KG-98/2 Cluster-II due to COVID-19 impact as manufacturing of subsea items and well completion got delayed.
  • Decline in production from Mandapeta, Pasarlapudi&Endamuru field in Rajahmundry.
  • Less than envisaged production from Dahej&Gandhar field in Ankleshwar.
  1. Natural gas production by OILin the nomination block is higher than monthly target of Aug’21 (2.20%) but less than when compared April – Aug’21 target (4.46%). Also, it is higher than actual production in corresponding month and period of last year i.e. Aug’20 (36.05%) & Apr-Aug’20 (13.36%). Reasons for shortfall in production as compared to target is as under:
  • Low upliftment/demand of gas by the major customers.
  1. Natural gas production by Pvt. /JVs companiesin the PSC/RSC/CBMregime is higher than actual production in corresponding month and period of last year i.e. Aug’20 (186.22%) & Apr-Aug’20 (200.84%). Also, it is higher than cumulative April – Aug’21 target (4.11%) but less than monthly target of Aug’21(7.68%). Increase in gas production with respect to Apr-Aug’21 target and corresponding period of last year is due to production from new fields D-34 and Satellite Cluster of KG-DWN-98/3 where production commenced in Dec-2020 and April-2021 respectively. Besides, there is higher offtake from gas fields (AAP-ON-94/1, KG-OSN-2001/3 & CB-OSN-2003/1) that led to increase in the production.
  1. Crude Oil Processed (Crude Throughput)

Crude Oil Processed during August2021 was 18438.58TMT, which is 14.17% higher than August 2020but 0.33% lower than the target for the month.Cumulative crude throughput during April-August, 2021 was95077.05TMT, which is 15.30% higher when compared with the production of corresponding period of last year but 2.55% lower than target for the period. Refinery-wise details of the crude throughput and capacity utilization during the month of August 2021 vis-à-vis August 2020 are given at Annexure-III and Annexure-IV. Company-wise crude throughput for the month of August2021and cumulatively for April-August, 2021vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.

Figure 3: Crude Oil Processed (Crude Throughput)

Table 3: Crude Oil Processed (Crude Throughput) (in TMT)

Oil CompanyTargetAugust (Month)April- August (Cumulative)
2021-22 (Apr-Mar)*2021-222020-21% over last year2021-222020-21% over last year
Target*Prod.*Prod.Target*Prod.*Prod.
CPSE145812.8411034.699908.628722.76113.5958655.3352576.8044900.15117.10
IOCL70299.814962.974903.563949.64124.1529097.1627290.1822242.55122.69
BPCL30499.942620.002373.021763.37134.5713205.0011429.238774.42130.26
HPCL17199.691426.02777.981309.7159.406030.344085.636634.7761.58
CPCL10000.00780.00629.07561.68112.003640.003482.142613.44133.24
NRL2750.35240.17211.69225.7293.781107.891078.611070.24100.78
MRPL15000.001000.001006.57905.22111.205550.005181.673534.42146.61
ONGC63.045.536.747.4390.7824.9429.3530.3296.81
JVs18021.001536.001709.931498.34114.127490.008246.346135.51134.40
BORL7000.00600.00598.10450.87132.652870.002812.122021.89139.08
HMEL11021.00936.001111.831047.47106.144620.005434.224113.62132.10
Private78008.075928.576820.025928.57115.0431423.5534253.9131423.56109.01
RIL60940.964389.745109.624389.74116.4023967.8925891.7623967.89108.03
NEL17067.111538.831710.411538.83111.157455.678362.157455.67112.16
TOTAL241841.9118499.2618438.5816149.67114.1797568.8895077.0582459.22115.30

Note:  Totals may not tally due to rounding off.*: Provisional

3.1 CPSE Refineries’ crude oil processed is higher than actual production in a corresponding month and period of last year i.e. Aug’20 (13.59%) & Apr-Aug’20 (17.10%). However, it is less than the monthly target of Aug’21 (10.2%) as well as the April – Aug’21 target (10.36%). Reasons for shortfall in production as compared to target are as under:

  • IOCL-Guwahati: Monthly Crude processed lower due to Crude Distillation Unit (CDU) stabilization delay.
  • IOCL-Barauni&Digboi: Monthly Crude processed lower due to deferment of M&I shutdown
  • IOCL-Gujarat, Mathura, Panipat: Monthly Crude processed lower due to lower product demand
  • IOCL-Paradip: Monthly Crude processed lower due to revamp shutdown.
  • BPCL-Kochi: Monthly Crude processed lower due to CDU-2 turnaround.
  • HPCL, Mumbai: Monthly Crude processed lower due to continued shutdown of one of the crude processing unit. Most of the other units are also under planned shutdown for revamp jobs.
  • HPCL, Viskah: Monthly Crude processed lower due to continued shutdown of one of the primary crude processing unit
  • CPCL-Manali: Monthly Crude processed lower due to Refinery-III M&I shutdown. And lower demand due to COVID-19 lockdown.
  • MRPL-Mangalore: Monthly Crude processed lower due to secondary unit throughput.

3.2       JV refineries’ crude oil processed higher than the monthly target of Aug’21 (11.32%) as well as the April – Aug’21 target (10.1%). Also, it is higher than actual production in the corresponding month and period of last year i.e. Aug’20 (14.12%) & Apr-Aug’20 (34.4%).

3.3       Private refineries’ crude oil processed higher than actual production in corresponding month and period of last year i.e. Aug’20 (15.04%) & Apr-Aug’20 (9.01%).

  1. Production of Petroleum Products

Production of Petroleum Products during August 2021 was 19560.19 TMT, which is 9.05% higher than the production of August 2020 but 2.72% lower when compared with a target for the month. Cumulative production during April-August, 2021 was 100237.95TMT, which is 12.26% higher when compared with the production of the corresponding period of last year but 3.25% lower than the target for the period. Unit-wise production of petroleum products is given in Annexure-V. Company-wise production for the month of August 2021and cumulatively for April-August, 2021 vis-à-vis the same period of last year has been shown in Table-4 and month-wise in Figure-4.

Table 4: Production of Petroleum Products (TMT)

Oil CompanyTargetAugust (Month)April- August (Cumulative)
2021-22 (Apr-Mar)*2021-222020-21% over last year2021-222020-21% over last year
Target*Prod.*Prod.Target*Prod.*Prod.
CPSE137873.4410447.419650.598356.41115.4955522.0149993.8142542.18117.52
IOCL66984.334740.854832.053811.73126.7727776.4126125.7321230.02123.06
BPCL29279.042514.212309.511705.24135.4412645.6511120.418434.52131.84
HPCL16019.551332.71691.691319.9752.405620.103850.156319.9160.92
CPCL9279.11721.72607.20486.72124.763364.683172.502362.23134.30
NRL2749.06240.06207.85227.8391.231107.371043.351075.7496.99
MRPL13502.33892.58995.82797.80124.824984.074653.663090.84150.56
ONGC60.025.276.477.1390.7423.7428.0228.9396.86
JVs16361.001410.001604.491354.88118.426868.007647.475684.08134.54
BORL6095.00523.00554.54363.62152.512493.002498.721710.19146.11
HMEL10266.00887.001049.94991.26105.924375.005148.753973.89129.56
Private93222.977843.657970.127843.65101.6139311.3240879.6839311.32103.99
RIL76683.166361.446285.646361.4498.8132056.9632772.9232056.96102.23
NEL16539.811482.211684.481482.21113.657254.368106.767254.36111.75
Total Refinery247457.4119701.0619225.1917554.94109.51101701.3498520.9687537.59112.55
Fractionators4516.39406.30335.00381.8987.721902.441716.991750.1198.11
TOTAL251973.8020107.3619560.1917936.83109.05103603.77100237.9589287.69112.26

Note:  Totals may not tally due to rounding off. *: Provisional

Figure 4: Monthly Refinery Production of Petroleum Products

  1. Production of petroleum Products by Refineries is higher than actual production in corresponding month and period of last year i.e. Aug’20 (9.51%) & Apr-Aug’20 (12.55%). However, it is less than monthly target of Aug’21 (2.42%) as well as April – Aug’21 target (3.13%).
  1. Production of petroleum Products by Fractionators is less than actual production in corresponding month and period of last year i.e. Aug’20 (12.28%) & Apr-Aug’20 (1.89%). However, it is also less than monthly target of Aug’21 (17.55%) as well as April – Aug’21 target (9.75%).

BNE ADMIN